Côte d'Ivoire, Liberia, Sierra Leone and Guinea Electricity Interconnection Project/Rural Electrification - Guinea Component (CLSG/VER): Monitoring and supervision of rural electrification works ( 2020 - 2023 )
As part of the Côte d'Ivoire, Liberia, Sierra Leone and Guinea Electricity Interconnection Project, leading to the construction of a 1,357 km, 225 kV double circuit transmission line to connect the four national electricity networks, this project assisted in the establishment of a dynamic electricity market in the West African sub-region and in securing the electricity supply of the participating countries. Ginger SOFRECO, on behalf of and in the best interest of the contracting authority (EDG), was responsible for monitoring and supervising the execution of the entire rural electrification component.